This page shows the details for an Asbestos Case.
Case No.: 08-030 Emergency: NO Amendment: 0 | Date Received: 1/22/2008 |
Site Name: TransAlta Centralia Generation LLC | Date Approved: 1/22/2008 |
Receipt No.: Receipt 18147 | Date Paid: 1/24/2008 |
SWCAA FEE: $250.00 | SWCAA Staff: Not Yet Assigned |
Site Address: 913 Big Hanaford Rd Centralia, WA 98531 LEWIS COUNTY |
|
Facility Type: Industrial | |
Prior Use: Industrial | Present Use: Industrial |
Project Type: Renovation | |
Start Date: 2/5/2008 | Completion Date: 2/21/2008 |
Work Days: | Hours Worked: |
SQ Feet: 2000 | Linear Feet: 900 |
Material Type: | |
Controls: | |
Comments: Mag. pipe insulation, air cell, boiler insulation |
Abatement Contractor: Performance Abatement Services - Tigard | LNI Certification No: |
Phone No.: | |
Property Owner: TransAlta Centralia Generation 913 Big Hanaford Rd Centralia, WA 98531 |
Submitted by: - | Representing: |
Email: | Phone No.: |