Case No.: 11-210 Emergency: YES Amendment: 0 | Date Received: 5/24/2011 |
Site Name: Tidewater Barge Lines | Date Approved: 5/24/2011 |
Receipt No.: 23637 | Date Paid: 5/24/2011 |
SWCAA FEE: $500.00 | SWCAA Staff: Not Yet Assigned |
Site Address: North Bank of the Columbia River Camas, WA 98607 CLARK COUNTY |
|
Facility Type: Industrial | |
Prior Use: Miscellaneous | Present Use: Miscellaneous |
Project Type: Removal | |
Start Date: 5/25/2011 | Completion Date: 6/1/2011 |
Work Days: MTWTF | Hours Worked: |
SQ Feet: 0 | Linear Feet: 450 |
Material Type: Mag Pipe, Other:Wire wrap | |
Controls: NP Enclosure, Water, Half Mask, HEPA Vac | |
Comments: Gerry approved emergency |
Abatement Contractor: 3 Kings Environmental Inc. | LNI Certification No: |
Phone No.: | |
Property Owner: US Coast Guard , WA |
Submitted by: - | Representing: |