Case No.: 13-204 Emergency: NO Amendment: 2 | Date Received: 6/17/2013 |
Site Name: Resident | Date Approved: 6/18/2013 |
Receipt No.: | Date Paid: |
SWCAA FEE: $0.00 | SWCAA Staff: Not Yet Assigned |
Site Address: 8315 NE 219th St Battle Ground, WA 98604 CLARK COUNTY |
|
Facility Type: Residential | |
Prior Use: Residence | Present Use: Residence |
Project Type: Removal | |
Start Date: 6/24/2013 | Completion Date: 6/28/2013 |
Work Days: MTWTF | Hours Worked: |
SQ Feet: 1225 | Linear Feet: 40 |
Material Type: Popcorn Ceiling, Sheet Vinyl, Other:Sheetrock | |
Controls: Water, CP Demand, HEPA Vac | |
Comments: A1 date change recvd 6/10/13 A2 date change Recvd email 6/17/13 on hold today start again 18th |
Abatement Contractor: Correctional Industries Environmental | LNI Certification No: |
Phone No.: | |
Property Owner: WA Dept. of Transportation PO Box 1709 Vancouver, WA 98668 |
Submitted by: - | Representing: |