This page shows the details for an Asbestos Case.
Case No.: 14-151 Emergency: NO Amendment: 1 | Date Received: 4/23/2014 |
Site Name: Northwest Pipeline - Battle Ground | Date Approved: 4/23/2014 |
Receipt No.: 28093 | Date Paid: 4/11/2014 |
SWCAA FEE: $100.00 | SWCAA Staff: Not Yet Assigned |
Site Address: 8907 NE 219th St Battle Ground, WA 98604 CLARK COUNTY |
|
Facility Type: Industrial | |
Prior Use: Miscellaneous | Present Use: Miscellaneous |
Project Type: Removal | |
Start Date: 4/30/2014 | Completion Date: 4/30/2014 |
Work Days: W | Hours Worked: |
SQ Feet: | Linear Feet: 80 |
Material Type: Other:Coal tar based pipe coating | |
Controls: Wrap & Cut, Water, Other: 1/2 mask APR | |
Comments: A1 date change |
Abatement Contractor: Keystone Contracting, Inc. | LNI Certification No: |
Phone No.: | |
Property Owner: Williams Pipeline 239 Zandecki Rd Chehalis, WA 98532 |
Submitted by: - | Representing: |
Email: | Phone No.: |