Asbestos Case Details

This page shows the details for an Asbestos Case.

CASE

Case No.: 18-508   Emergency: NO   Amendment: 9 Date Received: 6/6/2019
Site Name: School - 813 Eshorn Rd Date Approved: 6/6/2019
Receipt No.: Date Paid:
SWCAA FEE: $0.00 SWCAA Staff: Not Yet Assigned

SITE INFORMATION

Site Address:
   813 Eshorn Rd
   Centralia, WA 98531
   LEWIS COUNTY
Facility Type: School  
Prior Use: School Present Use: School

PROJECT

Project Type: Removal
Start Date: 6/10/2019 Completion Date: 9/30/2019
Work Days: MTWTF Hours Worked:
SQ Feet: 80000 Linear Feet:
Material Type: Mag Pipe, Other:
Controls: NP Enclosure, Mini Enclosure, Wrap & Cut, Water, HEPA Vac 
Comments: A1 date change A2 date change and hours 6am-4pm and different supervisor A3 for 10/12 working from 6pm-12pm after Friday 10/12 resume schedule as of Monday-Thursday 6am-4pm A4 adding Friday workshifts 6am-10am while still working Mon-Thurs from 6am-4pm A5 added an hour to schedule today A6 MTWTHF 700am-330pm A7 on hold from 11/17/18-11/25, to resume 11/26/18 11/29/18 on hold 11/28/18 and 11/29/18 to resume 11/30/18 A8 Phase 1 completed 12/05/18, project to resume in July 2019 12/14/18 a little more work to do so on hold for now until next week 12/19/18 on hold at least until July 2019 04/02/19 should only be out there until Thursday New supervisor is Dean Maijala and cert is ABAS00024206 04/09/19 on hold 06/04/19 off hold back on project 6/10/19 hours and days still the same A9 date change

CONTRACTORS/OWNER

Abatement Contractor: Northstar CG, LP LNI Certification No:
Phone No.:
Property Owner: Centralia School District
   PO Box 610
   Centralia, WA 98531

SIGNATURE

Submitted by:  -  Representing:
Email: Phone No.: