Asbestos Case Details

This page shows the details for an Asbestos Case.

CASE

Case No.: 21-166   Emergency: NO   Amendment: 3 Date Received: 5/27/2021
Site Name: Columbia Bank - 1100 Harrison Ave Date Approved: 5/27/2021
Receipt No.: Date Paid:
SWCAA FEE: $0.00 SWCAA Staff: David Joyner

SITE INFORMATION

Site Address:
   1100 Harrison Ave
   Centralia, WA 98731
   LEWIS COUNTY
Facility Type: Commercial  
Prior Use: Commercial Present Use: Commercial

PROJECT

Project Type: Removal
Start Date: 4/26/2021 Completion Date: 6/30/2021
Work Days: MTWT Hours Worked:
SQ Feet: Linear Feet:
Material Type: Other:
Controls: Mini Enclosure, Water, HEPA Vac 
Comments: A1 4/15/21 on hold recvd amendment on fax at 12:16pm today 5/6/21 A2 date change and hours-project is ready to start next phase-off hold MTWTF 6 am - 230 pm 5/6/21 back on hold A3 change end date 06/11/21 completed

CONTRACTORS/OWNER

Abatement Contractor: KD & S Environmental, Inc LNI Certification No:
Phone No.:
Property Owner: Columbia Bank
   5210 74th St W
   Suite B
   Lakewood, WA 98499

SIGNATURE

Submitted by:  -  Representing:
Email: Phone No.: