This page shows the details for an Asbestos Case.
Case No.: 23-837 Emergency: NO Amendment: 2 | Date Received: 12/19/2023 |
Site Name: 24599 | Date Approved: 12/19/2023 |
Receipt No.: | Date Paid: 12/15/2023 |
SWCAA FEE: $0.00 | SWCAA Staff: Danielle Kreps |
Site Address: 2010 Main Street Vancouver, WA 98660 CLARK COUNTY |
|
Facility Type: Commercial Business | |
Prior Use: Commercial | Present Use: Commercial |
Project Type: Removal | |
Start Date: 12/20/2023 | Completion Date: 12/20/2023 |
Work Days: W | Hours Worked: 2PM - 7PM |
SQ Feet: 45 | Linear Feet: 0 |
Material Type: VAT, Other:mastic | |
Controls: NP Enclosure, Water, HEPA Vac | |
Comments: Project has been pushed to to morrow afternoon instead. |
Abatement Contractor: Rose City Contracting, Inc | LNI Certification No: IR-23-2629B |
Phone No.: | |
Property Owner: MIKE AND SHARON PROPERTIES LLC , |
Submitted by: David Chaff - Project Coordinator | Representing: Rose City Contracting |