Case No.: 24-231 Emergency: NO Amendment: 3 | Date Received: 5/24/2024 |
Site Name: 24506 | Date Approved: 5/24/2024 |
Receipt No.: 156672064 | Date Paid: 5/24/2024 |
SWCAA FEE: $37.00 | SWCAA Staff: Stephanie Hungerford |
Site Address: 11814 NE 117TH AVE Vancouver, WA 98662 CLARK COUNTY |
|
Facility Type: Church | |
Prior Use: Church | Present Use: Church |
Project Type: Removal | |
Start Date: 4/22/2024 | Completion Date: 5/31/2024 |
Work Days: M T W Th F | Hours Worked: 8AM - 6PM |
SQ Feet: 40325 | Linear Feet: 0 |
Material Type: VAT, Other:Texture, Mastic, Cove Base Mastic, | |
Controls: NP Enclosure, Water, HEPA Vac | |
Comments: extending end date due to delays, Project Completed on 05/31/2024 - The Chaplain building was completed on 5/31/2024. The house and sanctuary still need abatement (different permit). |
Abatement Contractor: Rose City Contracting, Inc | LNI Certification No: 46449617040623 |
Phone No.: | |
Property Owner: Brush Praire Baptist Church , |
Submitted by: David Chaff - | Representing: Rose city contracting |
Email: operations@rosecitycontracting.com | Phone No.: 503-685-9505 |