Recently Issued Air Discharge Permits
Facilities are listed in alphabetical order by final permit date.
These permits have been recently issued final by the Southwest Clean Air Agency. These permits are open for appeal
to the Pollution Control Hearing Board until 30 days after the date the permit
was issued as shown below. For information on the appeals process, click here.
Lakeside Industries, Inc. - Pelletizing Plant - Longview
PERMIT NO: 24-3647
Application Notice:
VIEW
Air Discharge Permit:
VIEW
Tech Support Document:
VIEW
Notice on Web Page:
None
Final Date:
Wednesday, June 5, 2024
Final Posted to Web:
Friday, June 7, 2024
PHCB Appeal Period Ends:
Friday, July 5, 2024
Public Comments:
None
Public Comment Responses:
None
Agency Contact:
Wess Safford
SEPA DETERMINATION NO: Longview E-2024-3
Lead Agency:
City of Longview
Checklist:
None
Action:
SEPA-DNS
Register Notice:
None
Final Date:
Tuesday, May 28, 2024
Determination:
VIEW
NOTES:
Portable asphalt shingle pelletizing plant.
Thompson Metal Fab, Inc. - Vancouver
PERMIT NO: 24-3646
Application Notice:
VIEW
Air Discharge Permit:
VIEW
Tech Support Document:
VIEW
Notice on Web Page:
None
Final Date:
Wednesday, June 5, 2024
Final Posted to Web:
Friday, June 7, 2024
PHCB Appeal Period Ends:
Friday, July 5, 2024
Public Comments:
None
Public Comment Responses:
None
Agency Contact:
Wess Safford
SEPA DETERMINATION NO: SWCAA 24-021
Lead Agency:
SWCAA
Checklist:
None
Action:
SEPA-DNS
Register Notice:
None
Final Date:
Wednesday, June 5, 2024
Determination:
VIEW
NOTES:
Replacement of an existing plasma cutter.